F5 BIG-IP i7800 to BIG-IP r5900 Replacement


F5 LOAD BALANCER REPLACEMENT — FIRST-TIME GUIDE

BIG-IP i7800  →  BIG-IP r5900

A click-by-click migration runbook for your first HA-pair hardware swap

 

The plan in one sentence:  your two i7800s are a pair — you'll remove the standby one and plug the first r5900 into the team; prove the new box can carry everything alone for real; then remove the second i7800 and plug in the second r5900. Users never see the change.

 

F5 load balancer replacement guide showing the migration from BIG-IP i7800 to BIG-IP r5900, with network appliances, a data center background, and upgrade direction for network engineers.

 

 

Field

Detail

Document

Click-by-click runbook for a first-timer

Pair names used in examples

i7800-A (currently ACTIVE) · i7800-B (standby) → r5900-1, r5900-2

Method

Rolling member replacement — one box at a time

Expected outage

None for users (a short controlled failover is part of testing)

Before you start

Read Sections 1–3 fully; skim the tests in Section 8

Version

v1.0

 

1. Read This First — What You Are Actually Doing

Your company has two i7800 load balancers guarding the apps. They work as a team called an HA pair: one is ACTIVE (handles all traffic), the other is STANDBY (a hot copy doing nothing until needed). If the active box dies, the standby takes over in seconds — that takeover is called a failover, and it's the whole trick this migration relies on.

Instead of taking both old boxes out at once (scary, all-or-nothing), you'll swap them one at a time so one working box is always live:

Moment

ACTIVE box

STANDBY box

Who serves users?

Today

i7800-A

i7800-B

i7800-A

After Night 1 (Phase 1)

i7800-A

r5900-1

i7800-A — never changed

During the proof test

r5900-1 (for a few minutes)

i7800-A

r5900-1 proves itself, then you hand it back

Final

r5900-1

r5900-2

r5900-1

 

THE GOLDEN RULE:  Rule of thumb for a first-timer: NEVER remove the ACTIVE box. Every phase only ever touches the STANDBY one. Active boxes only change hands during a deliberate, planned failover you trigger yourself.

 

1.1 FAQ a first-timer usually asks

Question

Straight answer

Will the website go down?

Not if HA is healthy. Traffic moves between members via a heartbeat you test before trusting it.

What if the new box is wrong/misconfigured?

It stays standby, users unaffected. You fix it with zero urgency.

What is the worst that can happen?

A failed proof failover — you simply fail traffic back to the old i7800, still racked and staged. That's the whole design.

How long does it take?

Phase 1: one evening change window. Phase 2: another window, usually days later.

 

2. What You Need Before Touching Anything

2.1 On your laptop

  • A browser (Chrome/Edge) — all F5 management is done over HTTPS web pages.

  • An SSH client — Windows: use PuTTY (Host Name: the box's mgmt IP, Port 22, Connection type SSH) or PowerShell's built-in ssh. macOS/Linux: ssh admin@<ip>.

  • A screenshot folder and a plain-text scratch file — every step you'll capture before/after evidence; rollback instructions will paste them back later.

  • A printed/written rollback trigger list agreed with your lead (examples: sync stuck more than 15 min → stop; test VIP not answering in 2 min → roll back).

2.2 Accounts, addresses and names to pre-write here

Item

Value (fill in BEFORE the night)

i7800-A mgmt IP / login

______________________

i7800-B mgmt IP / login

______________________

F5OS mgmt IP of r5900-1 (new!)

______________________

Tenant (BIG-IP) mgmt IP on r5900-1

______________________

3 test applications to watch

______________________

Your core switch / distribution IPs for ping tests

______________________

 

3. The Jargon You'll Meet — In Plain Words

Term you'll see

What it really is

UCS file

A full backup archive of the BIG-IP config (kind of like a zip of your whole setup) — the restore file for the new box.

platform-migrate

A UCS-restore option meaning: 'this came from different hardware' — adapts interface naming etc.

Device trust

The SSL-certificate handshake that lets two boxes sync safely; you click to accept each other, like friending on a network.

Device group + config-sync

The set of boxes sharing config automatically. Whenever A changes something, B is copied within seconds.

Traffic group

The bundle of IPs/services that fails over together ('traffic-group-1' by default).

Failover (forced)

You deliberately make the active box stand down so the standby takes over — the main tool of this migration.

Self-IP

An IP the balancer itself owns on a VLAN — this is what neighbor devices talk to.

Virtual Server (VIP)

The public-facing IP+port combo your apps sit behind.

Tenant (rSeries only)

The virtual BIG-IP instance running inside the r5900's operating system (F5OS). You build the tenant first, then log into it like a normal BIG-IP.

 

4. The One Big Thing to Understand About the r5900

The old i7800 boots straight into BIG-IP — one screen does everything. But rSeries boxes run two layers: F5OS, the appliance's own operating system (where the power, fans, software images and tenants live), and inside it a BIG-IP tenant — which is where your real work happens.

So there are two admin pages (two different IPs on the same box):

Layer

What it looks like

What you do there

F5OS (outer shell)

Blue-toned platform UI at https://<r5900 mgmt IP>

Install the tenant image, deploy the tenant (click 'Deploy'), manage power/diag

BIG-IP tenant (inner)

Classic F5 TMUI you already know from the i7800s

Everything else: config, VIPs, HA, sync

 

FIRST-LOGIN:  All F5OS default-account changes: First login to F5OS forces a password change for the admin account. The tenant's BIG-IP mgmt creds are set when you fill the tenant form.

 

5. Phase 0 — Pre-work Weekend (nothing is unplugged)

5.1 Back up the configuration on both i7800s

You make UCS archives (full backups) BEFORE anything changes. Do this on BOTH boxes, one after the other.

Step 1 — Open the BIG-IP web page of i7800-A

In your browser:  https://<i7800-A mgmt IP>. Log in with admin.

Step 2 — Find the archive manager

CLICK PATH:  System  >  Archives  >  UCS List   (then click the "Create" button)

Step 3 — Name it clearly, create it

Example file name:  pre-migration-i7800A-2026-10-27.ucs — then click OK. BIG-IP builds the archive in about a minute.

Step 4 — Download the archive to your laptop

CLICK PATH:  System  >  Archives  >  UCS List  >  click the file name  >  "Download"

Step 5 — Repeat on i7800-B

Same four steps. You should end with two files on your laptop, dated today. Call them out in your change ticket.

GOOD RESULT:  You now have one .ucs file per old box. If everything else goes wrong tonight — these files are the safety net.

 

5.2 Stand up the r5900 (in the lab first if you can)

Step 1 — Log into F5OS on r5900-1

Point your browser at https://<r5900-1 F5OS mgmt IP> (you / your DC team set this IP when racking). Log in; first login makes you set a new admin password.

Step 2 — Upload the BIG-IP tenant image

CLICK PATH:  Software Management  >  Tenant Images  >  Import  >  choose the BIG-IP ISO matching your i7800's TMOS version (or newer, F5-supported)  >  Upload

NOTE:  Match or exceed the i7800's TMOS version. Example: pair runs 17.1.x → pick 17.1.x or a maintenance release of the same train. Versions live at System > About on the old UI if you need to check.

 

Step 3 — Deploy the tenant

CLICK PATH:  Tenant Management  >  Tenant Deployments  >  "Deploy" button

In the form fill in:

  • Name:  bigip1 (whatever you like — the tenant name will show up on the platform UI)

  • Type:  BIG-IP   ·   Image:  pick the ISO you just imported

  • Management IP / netmask / gateway:  the tenant mgmt details you planned in Section 2.2

  • VLANs to trust + CPU/RAM:  leave at the recommended sizing for this platform

Click Deploy, then wait — starting takes a few minutes. Watch the Status column.

GOOD RESULT:  Tenant Status flips to Running. Bonus: hit the tenant mgmt IP in a fresh tab — you should see the classic BIG-IP login page (same look as the i7800s!).

 

Step 4 — Restore the i7800 config onto the tenant (the clever bit)

SSH to the TENANT (not F5OS this time — the tenant's mgmt IP):

ssh admin@<tenant-mgmt-ip>

tmsh load sys ucs /var/local/ucs/<your-backup>.ucs platform-migrate

NOTE:  You'll be asked to copy the UCS file up first:  from your laptop, scp the archive to admin@<tenant-mgmt-ip>:/var/local/ucs/ — use your file's real name.

 

When it finishes, log back into the tenant's web UI and edit interface references: port numbers/names on the r5900 are different from the i7800 — open:

CLICK PATH:  Network  >  Interfaces  >  Interface List   — check every entry shows a real physical port of the r5900

CLICK PATH:  Network  >  VLANs  >  Self IPs   — make sure each self-IP's VLAN binds to the ports you-cabled-for-it

Do NOT enable config-sync to the old pair yet — that belongs to Night 1.

6. Phase 1 — Night 1: Swap the Standby (i7800-B out, r5900-1 in)

Remember the Golden Rule: tonight you only ever touch the STANDBY box. i7800-A keeps serving every user all night.

6.1 Confirm who's who before unplugging anything

Step 1 — Check status via web

On i7800-A's web UI, top panel shows: BIG-IP - Active. Also:

CLICK PATH:  Device Management  >  Devices   — you'll see both boxes listed; the column 'Sync Status' should say In Sync

GOOD RESULT:  If everything says Active on A and In Sync — you're good to proceed.

 

Step 2 — Same check via SSH (this is the test you'll use all night)

ssh admin@<i7800-A-mgmt-ip>

tmsh show cm failover-status

Look at the Failover traffic-group-1 line — it should say 'active device i7800-A' and ConfigSync 'In Sync'. Text output like this means YES:

Failover:      active         |  ConfigSync:  In Sync

6.2 Park i7800-B safely

Step 1 — Take i7800-B out of the data path

In the middle of the UI click: Device Management > Devices > i7800-B > open the device page > click the Force Offline button. Go to its interfaces (Network > Interfaces) and disable any VLAN-facing ports. Leave the box powered on with management live for rollback reasons.

Step 2 — Remove it from the device group

CLICK PATH:  Device Management  >  Device Groups  >  click your sync group  >  remove i7800-B from Members list  >  Save

Step 3 — Break the trust from i7800-A's side

CLICK PATH:  Device Management  >  Device Trust  >  Peer List  >  tick i7800-B  >  remove/delete

GOOD RESULT:  Device Management > Devices on i7800-A now shows ONLY i7800-A, In Sync, Active. Users are stale to this — nothing in production changed.

 

6.3 Introduce r5900-1 into the team

Step 1 — Cable it per the interface plan

Physical move per Section 5.2's port table. On the r5900 tenant: Network > Interfaces lights up the new links.

Step 2 — Let i7800-A trust r5900-1 (the friend request)

On i7800-A's web UI:

CLICK PATH:  Device Management  >  Device Trust  >  Peer List  >  "Add ..."  >  type r5900-1's tenant mgmt IP and admin creds  >  Retrieve Device Information  >  Device Certificate matches? Yes  >  Add Device

Step 3 — Add r5900-1 to the sync group

CLICK PATH:  Device Management  >  Device Groups  >  your group  >  move r5900-1 into the Members list  >  Save

Step 4 — Fire the first full sync (copies EVERYTHING from A to r5900-1)

CLICK PATH:  Device Management  >  Overview  >  click r5900-1  >  "Sync Device to Group" (or: it may already be buttoned as 'Sync' on the overview row)

Prefer the CLI? Same thing in one line (run this on i7800-A):

tmsh run cm config-sync to-group <your-device-group-name> full-sync

Step 5 — Wait — then check sync on BOTH sides

Give it a minute or two, then on i7800-A and r5900-1 run:

tmsh show cm failover-status        # 'ConfigSync: In Sync' is what you want

tmsh show cm device | grep -i sync   # quick view both members show Enabled sync

GOOD RESULT:  Both screens: 'In Sync'. Devices page shows 2 boxes: A Active, r5900-1 Standby.

 

6.4 THE proof: force traffic onto r5900-1 — deliberately

This is the moment of truth: you're going to ask A to stand down for a few minutes, so users actually run on the NEW hardware — and you'll watch them do it safely. Do it inside the low-traffic change window you booked.

Step 1 — On i7800-A, force yourself to standby

ssh admin@<i7800-A-mgmt-ip>

tmsh run sys failover standby

The pair flips: r5900-1 becomes ACTIVE. i7800-A shows Standby. Gratuitous ARPs announce: traffic starts hitting r5900-1 automatically.

Step 2 — Watch users flow — the five-minute checklist

Run these from your SSH to r5900-1 AND from inside your network:

Test

How

Looks good when

VIP answers

curl -k http://<one-VIP-IP>/   from your laptop

App homepage HTML/headers return

Pools healthy

tmsh show ltm pool   (on r5900-1)

Availability for each pool = green / available

Live traffic

tmsh show sys connection | head

Real session rows flying past

Peer pinging

ping -I <r5900-1 self-IP> <core gateway IP>

0% loss

GUI view

UI on r5900-1: Local Traffic > Virtual Servers list

All circles/icons green (available)

 

Step 3 — Hand traffic back

ssh admin@<i7800-A-mgmt-ip>   then:   tmsh run sys failover online

Wait 30 seconds, re-run  tmsh show cm failover-status  on both, confirm A is active again, r5900-1 standby, In Sync. Screenshot both.

GOOD RESULT:  Milestone! r5900-1 officially carried 100% of real production and nobody noticed. This proof is what makes Phase 2 a formality, not a gamble.

 

7. Phase 2 — Night 2: Remove i7800-A, Add r5900-2

Everything is the same pattern, roles reversed: r5900-1 has proven itself so it's allowed to become the active member, and this time the STANDBY being replaced is i7800-A.

7.1 Hand control to r5900-1 (permanently this time)

ssh admin@<i7800-A-mgmt-ip>   then:   tmsh run sys failover standby

Step 1 — Confirm r5900-1 active & healthy:  same commands as 6.1/6.4

Step 2 — Park i7800-A like you parked B: Force Offline, remove from group, remove from trust

Click paths are identical to 6.2 — just pointing at i7800-A this time.

Step 3 — Leave i7800-A powered-on in the rack for now (don't pull it yet — see Rollback)

7.2 Stand up r5900-2 as the new standby

Clone of Section 5.2 and 6.3 applied to r5900-2:

  • Rack r5900-2; deploy tenant per your file; platform-migrate the UCS; fix interface mapping; license the tenant.

  • Cable its ports in the same pattern; confirm link on Network > Interfaces.

  • From r5900-1: Add peer (Device Trust > Peer List > Add) → move r5900-2 into the group → run full-sync.

  • Verify: Devices page shows r5900-1 = Active, r5900-2 = Standby, In Sync on both; run the five-minute checklist of Section 6.4 one more time — now aimed at the FINAL pair.

GOOD RESULT:  Final state: two r5900s in a healthy pair. Both i7800s retired but still racked, staged for rollback.

 

8. Your Test Toolbox (keep this open on night shift)

8.1 SSH commands — copy/paste ready

What you want to know

Command

Good looks like ~

Which box is active / is sync healthy?

tmsh show cm failover-status

'active device' = expected unit · 'ConfigSync: In Sync'

Detailed per-member status

tmsh show cm device

Each device: Enabled · In Sync

Are my apps (VIPs) up on this unit?

tmsh show ltm virtual | grep -E "Virtual Server|Availability"

Availability: available for each VIP

Are pool members alive?

tmsh show ltm pool | grep -E "Ltm::Pool::\|Availability"

each pool/member Available / green

Is traffic really flowing?

tmsh show sys connection | head

fresh rows (not empty)

ARP answered for our VIPs?

tmsh show net arp | grep <VIP-IP>

one row with a MAC address per VIP

Can the box ping upstream?

ping -I <self-IP> <gateway-IP>

0% packet loss

The web hit users would do

curl -k http://<VIP-IP>/   (laptop)

your app's HTML/loading redirect comes back

 

8.2 GUI equivalents (if you prefer clicking)

Question

Where to click

Green means

Is this box Active?

top banner of its web UI

Says 'Active' opposite the box name

Sync state

Device Management > Devices table, Sync Status column

In Sync

VIP health

Local Traffic > Virtual Servers > Virtual Server List, Availability icon

Green circle = available

Pool/member health

Local Traffic > Pools > Pool List > select > Members

Green icons on every member

 

9. The Panic Button (Rollback)

Both phases share one core recovery move — the magic of keeping the old box racked:

9.1 During/after Phase 1 (mixed pair misbehaving)

Step 1 — Fail traffic back to the old active

ssh admin@<r5900-1-tenant-ip>   then:   tmsh run sys failover standby

(or on A:   tmsh run sys failover online)

Step 2 — Pop r5900-1 out of the group/trust (clicks of 6.2, reversed)

Step 3 — Re-cable i7800-B's interfaces, bring Back Online, re-add to trust + group, full-sync

Exact same buttons you already used in 6.3 — this time adding the OLD box.

9.2 During/after Phase 2

Same move: i7800-A is still racked next door. Bring it Back Online, trust it, add it to the group, sync. Traffic never left its side of the room to begin with.

WHEN TO PULL THE TRIGGER:  Decision gate: any test in Section 8 failing for more than 5 minutes inside the window = execute rollback, no debate. Documenting and re-planning later beats hero debugging in front of users.

 

10. Wrap-Up, the 'Being a Pro' Checklist

  • Two weeks later: Schedule the i7800s' quarantine (rack removal, licenses, warranty/RMA letters) only AFTER the final pair has been stable for days.

  • Update device lists in monitoring/SNMP/syslog, TAC cases, and license-portal notes; both i7800s decommissioned everywhere.

  • Refresh your backups: Export new UCS archives from both r5900s and file them next to the pre-migration ones.

  • Send the before/after facts (sized VLAN ports per the plan, TMOS versions, sync status screenshots) to your change ticket as evidence of a clean cutover.

 

You did a phased hardware migration and no user opened a ticket — that's the goal.